Budakeszi Wastewater Treatment Plant

KEOP-1.2.0/09-11-2011-0025
As part of the Budakeszi wastewater collection and treatment project, WHB constructed a modern, environmentally friendly wastewater treatment plant with increased capacity between 2014 and 2016.
Components of the complex investment:

installation and modernization of wastewater treatment technologies,
new pipeline sections and network upgrades,
modernization of mechanical and electrical systems,
reconstruction and capacity expansion of the entire plant.

The development contributed to a significant improvement in Budakeszi’s environmental quality and infrastructure.

  • Function Wastewater treatment plant
  • Location Budakeszi
  • Duration 2014-2016
  • Type of work General contractor